Intrusive FRAEW Survey

When nobody can say for certain what is behind the panels, the assessor has to look. Here is what that involves and what it adds to the job.

Get a quote

Opening up walls: the rules

Legal footing

PAS 9980:2022 expects the assessor to confirm the wall materials and fire protection, opening up where records don't show them.

Step-by-step guide, gov.uk

Timing

As part of the FRAEW, when drawings and specifications are missing or don't match what is on the building.

Step-by-step guide, gov.uk

Record kept

A record of each opening with photographs and findings, folded into the FRAEW report and its risk outcome.

FRAEW guidance, gov.uk

In short

An intrusive survey cuts small inspection openings in the wall so the assessor can see the insulation, cavity barriers and fixings. It is part of the FRAEW, not a separate report, and it adds access, labour and making good to the fee.

Why records are rarely enough

A drawing says what was meant to be built. Many blocks were altered during construction, reclad later, or simply built differently from the specification. Cavity barriers are left out, insulation is swapped for something cheaper, and fixings are not what the drawing shows. An assessor who relies on paper alone may reach the wrong answer, and a lender, insurer or the regulator may not accept it.

What happens on site

  • The assessor picks opening points to cover each wall type, around windows and at floor lines where cavity barriers should be
  • A contractor removes a panel or cuts a small section of render and insulation
  • The assessor records the layers, takes samples if needed for lab testing, and photographs everything
  • The opening is sealed and made weathertight the same day

Access

Low openings can be reached from the ground or a ladder. Higher ones need a mobile elevating work platform, which needs space and sometimes a road closure, or rope access, which suits tall blocks and tight sites. Access is often the largest single extra on an intrusive survey.

Effect on the fee

Opening up, access hire and laboratory testing are usually priced on top of the appraisal. Our cost page shows how they add up, and the calculator lets you add openings. Assessors rarely publish rates for these, so treat any figure as a guide until you have a written quote.

To keep the number of openings down, find every record you can first: drawings, specifications, warranties and photographs from any recladding. The PAS 9980 assessment page explains how those records are used.

Opening-up questions

How many openings will the assessor need?

Enough to see each different wall type, and more where the build-up seems to change across a face. A small block with one wall type may need two or three; an estate with several systems may need many more.

Who makes good the openings?

Usually a contractor working alongside the assessor, who opens and reseals each point. Make sure the quote says whether that is included, and who is responsible for weathertightness afterwards.

Do residents need to be told?

Yes. The government guide asks for advance notice of site visits and of which areas the intrusive work will affect. The step-by-step guide lists what to tell them.

Get a quote for an intrusive FRAEW

For managing agents, freeholders and directors of resident management or right to manage companies.

We look for one PAS 9980 assessor suited to your block. You learn who they are before they learn anything about you, and our part is free.

Leaseholder? Only the building owner or managing agent can order an FRAEW. Here's what to ask them for.