Cladding Remediation Data
How many blocks of 11 metres and over in England have unsafe cladding, and how many have been fixed, from the government's own monthly figures.
Where the backlog sits
At the end of September 2026, the government was monitoring 4,732 residential buildings of 11 metres and over with unsafe cladding. Works had finished on 1,878 and started on another 743. On 2,111, nothing had started.
Lower blocks are further behind. Of the 2,140 monitored buildings between 11 and 18 metres, 47% had started or finished works, against 63% of the 2,592 buildings over 18 metres. The newer Cladding Safety Scheme, which covers many of the lower blocks, had started works on 452 of its 1,524 eligible buildings.
Every one of these buildings needs an appraisal of its walls along the way, which is one reason FRAEW assessors are busy. If your block is waiting, read the rules on external walls and our article on funding for the appraisal.
Blocks monitored, September 2026
- Finished
- Started
- Not started
| Route | Eligible | Started or done | Finished |
|---|---|---|---|
| ACM cladding, high-rise | 516 | 505 | 481 |
| Building Safety Fund | 639 | 570 | 495 |
| Cladding Safety Scheme | 1,524 | 452 | 151 |
| Developer remediation | 2,682 | 1,416 | 613 |
| Social housing, self-funded | 692 | 527 | 450 |
Routes overlap, so they don't add up to the total.
Month by month in 2026
| Release | Monitored | Started or finished | Finished | Not started | Scheme blocks eligible | Scheme blocks started |
|---|---|---|---|---|---|---|
| April 2026 | 4,378 | 2,415 | 1,544 | 1,963 | 1,239 | 363 |
| July 2026 | 4,697 | 2,551 | 1,833 | 2,146 | 1,438 | 396 |
| September 2026 | 4,732 | 2,621 | 1,878 | 2,111 | 1,524 | 452 |
Reading the trend
Between April 2026 and September 2026 the number of finished buildings rose from 1,544 to 1,878. The total being monitored rose too, from 4,378 to 4,732, as more buildings were identified, and the Cladding Safety Scheme's eligible list grew from 1,239 to 1,524. New buildings are joining the list almost as fast as others leave it.
How we built this
Figures come from the Ministry of Housing, Communities and Local Government's Building Safety Remediation monthly data releases for April, July and September 2026, published under the Open Government Licence. We used the accessible versions of each release. We kept to 2026 releases. The monitored list changes as buildings are added and taken off, so read the department's technical notes before comparing with earlier years.
Get FRAEW quotes for your block
For managing agents, freeholders and directors of resident management or right to manage companies.
We look for one PAS 9980 assessor suited to your block. You learn who they are before they learn anything about you, and our part is free.
Leaseholder? Only the building owner or managing agent can order an FRAEW. Here's what to ask them for.
Received. Here's what happens next.
- We find a PAS 9980 assessor who covers the block and email you their name.
- If you say yes, we pass your details on. If not, the enquiry ends there.
- The assessor asks about height, wall types and records, then sends a written fee.