EWS1 · 20 Nov 2026 · 2 min read · FRAEW Quotes

In brief

B2 is the EWS1 option a signatory chooses when the fire risk from the external walls is high enough that remedial or other works are needed. Lenders often won't lend until works are done or funded, so a B2 usually holds up sales. The next step is the building owner's plan for the works and how they will be paid for.

Of the five options on an EWS1 form, B2 is the one nobody wants to see. It tells the lender that the walls contain combustible material and that the fire risk is high enough to need action.

B1 and B2

Both B options mean the walls include combustible materials. The difference is the signatory’s judgement of the risk:

  • B1: the risk is low enough that no remedial works are needed
  • B2: an adequate standard of safety isn’t achieved, and remedial or interim works are needed

The RICS FAQs explain each option.

What it means for a sale or remortgage

Most lenders treat a B2 as a reason to value the flat low, or not to lend at all, until works are done or a funded plan is in place. Buyers relying on a mortgage may not be able to proceed. Cash buyers sometimes do, at a lower price.

What happens next

The building owner is responsible for acting on the finding. The usual sequence:

  1. The FRAEW behind the EWS1 sets out what needs doing and how urgent it is
  2. The owner decides on remediation or other measures, and how to pay for them
  3. Funding is sought from the developer, a government scheme or the owner’s own resources
  4. Interim measures may be put in place while works are planned
  5. After the works, the walls are reassessed and a new form can be signed

Who pays for the works

For qualifying leases in buildings of 11 metres or 5 storeys and over, Schedule 8 of the Building Safety Act protects leaseholders from paying for cladding remediation and limits other relevant defect costs. Developers who signed up to remediate their buildings, and government schemes, cover many blocks.

If you are a leaseholder

Ask your managing agent for the FRAEW’s executive summary and the plan for works. Our leaseholder page has a letter you can use. If you are responsible for the building, our FRAEW quotes service can find an assessor to scope the works properly.

Sources

Get FRAEW quotes for your block

For managing agents, freeholders and directors of resident management or right to manage companies.

We look for one PAS 9980 assessor suited to your block. You learn who they are before they learn anything about you, and our part is free.

Leaseholder? Only the building owner or managing agent can order an FRAEW. Here's what to ask them for.

Your block and your details

By sending this form you agree that we'll use your details to find a local FRAEW assessor for you. We'll tell you who they are and ask you before passing your details on. See our privacy notice.

Get a quote